Surrey-Langley SkyTrain Construction Update: Test piling activities at Industrial Ave and 203 Street

Surrey-Langley SkyTrain Construction Update: Test piling activities at Industrial Ave and 203 Street

Surrey-Langley SkyTrain Construction Update: Test piling activities at Industrial Ave and 203 Street

To prepare for the construction of the Surrey Langley SkyTrain, early works are underway in the area. As part of early construction work, crews will complete “test piles” over a three-week period starting the week of September 23 to October 7, 2024.

Pile installation involves driving a long metal tube (pile) into the ground to provide the foundation for a structure. The purpose of the test piles is to provide geotechnical information for the design and construction of the new Langley City Centre Station.

What to expect:

Dates: Starting the week of September 23 to October 7, 2024.
Timing:  Monday to Saturday from 7 a.m. to 10 p.m.
Traffic:  No traffic impacts are expected
Impacts:  There may be a temporary increase in noise and vibration while this work is taking place. Monitoring personnel will be on site.